A new phase of line work is opening in Choisy-le-Roi
Published on
-Updated on
A second phase of line work begins the week of 19 October, lasting about 4 months. The right-of-way for the works in this phase shifts to the west side (Intermarché) of Avenue de Lugo. Its installation on the nights of 19 to 23 October may generate noise pollution.
Traffic remains two-way on Avenue de Lugo, but its access to and from the Voie de l'Epinette is temporarily neutralized during this phase. It is also occasionally closed towards the rue du Docteur Roux, depending on the progress of the work.
The route of lines 182 and 282 is temporarily adapted: the "8 mai 1945" stops are maintained on the avenue, but moved to the direct vicinity, and the "Docteur Roux" stop in the direction of Paris is removed.
Pedestrian and cycle paths are occasionally adapted and parking is temporarily neutralised along the construction sites.
Access to local residents and shops is maintained.